TABLE OF CONTENTS
7. ENVIRONMENTAL
COMPLAINT AND NON-COMPLIANCE
8. IMPLEMENTATION
STATUS OF ENVIRONMENTAL MITIGATION MEASURES
FIGURES
Figure 1 Project
General Layout
Figure 2 Air
and Noise Monitoring Locations
LIST OF APPENDICES
Weather and Meteorological Conditions during
Reporting Month |
|
|
|
i.
The Civil Engineering and Development
Department HKSAR has appointed MateriaLab Consultants
Limited (MCL) to undertake the Environmental Team services for the Project and implement
the EM&A works.
ii.
This Monthly EM&A report presents the
environmental monitoring and audit works for the period between 1 January and 31
January 2021. As informed by the Contractor, major activities in the reporting month
were:
Landscape works – irrigation
systems, tree and shrub planting
Breaches of the Action and Limit Levels
iii. Five Action Level exceedance for 24-hr TSP were
recorded in the reporting month. An exceedance were recorded at KER1 on 20 January
2021. Four exceedance were recorded at KTD2c on 4, 14, 20 and 26 January 2021.
iv. No Action / Limit Level exceedance was
recorded for 24-hr TSP at KTD1 in the reporting month.
v. No Action / Limit Level exceedance was
recorded for construction noise at KTD1, KTD2c and KER1 in the reporting month.
Complaint, Notification of Summons and Successful Prosecution
vi. No environmental complaint, notification of
summons and successful prosecution were received in the reporting month.
Reporting Changes
vii. There was no reporting change in the
reporting month.
Future Key Issues
viii. The key issues to be considered in the
coming reporting month include:
Potential environmental
impacts arising from the above construction activities are mainly associated
with construction dust, construction noise, water quality, waste management and
landscape and visual impacts.